Tie Lake Dam Project largely complete

The total cost for the project was $450,000

Following a tour of the new dam, RDEK Electoral Area B Director Stan Doehle (right) congratulates project lead Brian De Paoli, RDEK Engineering Technician (left) on the substantial completion of the project.

Following a tour of the new dam, RDEK Electoral Area B Director Stan Doehle (right) congratulates project lead Brian De Paoli, RDEK Engineering Technician (left) on the substantial completion of the project. — Photo courtesy RDEK

The Tie Lake Dam project is substantially complete and the new dam structure is in place.

Construction started earlier this fall and included raising the height of the dam to allow for more freeboard; installation of seepage control and a new spillway. “The larger size of the dam has reduced the risk of the dam being overtopped by high water as has nearly happened a couple of times in the past few years,” explains Engineering Technician Brian De Paoli.

As part of the project, the weir, known as a Cippoletti weir due to the v-shaped notch in its design, has been fenced. Although the dam height has been increased, the average lake level is not expected to change. “The dam height will help prevent issues during high water and flooding; however, at this time the structure is not intended to raise the level of the lake beyond the previous seasonal norms,” adds De Paoli.

RDEK Engineering Technician shows Electoral Area B Director Stan Doehle the new weir that has been installed as part of the Tie Lake Dam project.

RDEK Engineering Technician shows Electoral Area B Director Stan Doehle the new weir that has been installed as part of the Tie Lake Dam project. — Photo courtesy RDEK

“It is great to see this project completed. We now have a dam structure that meets the safety objectives of the Dam Safety Officer, and that will meet the needs of the community for years to come,” says Electoral Area B Director Stan Doehle. “We are also very grateful to the Community Works Fund for funding 86% of the project.”

Although the disturbed areas around the project site have been re-seeded, the RDEK will be back on site in the spring to undertake further vegetation measures and monitor the progress of the seeding.

“We would like to thank the residents and property owners of Tie Lake for their patience as we worked through the process of rebuilding the dam. We also would like to thank our consulting engineer Associated Engineering and our contractor Ironclad Construction for their efforts throughout the project,” adds De Paoli.

The total cost for the project was $450,000.

Related articles

Kootenay BizBlog, East Kootenay, West Kootenay, Financial, Technology MP Wayne Stetski calls for more funding for rural internet and wireless

Stetski called on the government to substantially increase its investment in rural connectivity in the 2019 budget saying, “rural Canadians deserve no less.”

Kootenay BizBlog, West Kootenay, Retail, Small Business, Technology Innov8 Digital Solutions Inc. acquires Lang Business Systems

Innov8 Digital Solutions Inc. is B.C.’s largest independently owned and operated office equipment sales and service organization

Kootenay BizBlog, West Kootenay, Castlegar, Education, Technology Selkirk College GIS Alumnus soars in new career

A geospatial analyst for Nelson’s Harrier Aerial Surveys, Landry is part of a team that provides high-precision surveying

View all articles

Comments