Tie Lake Dam Project largely complete

The total cost for the project was $450,000

by
Following a tour of the new dam, RDEK Electoral Area B Director Stan Doehle (right) congratulates project lead Brian De Paoli, RDEK Engineering Technician (left) on the substantial completion of the project.

Following a tour of the new dam, RDEK Electoral Area B Director Stan Doehle (right) congratulates project lead Brian De Paoli, RDEK Engineering Technician (left) on the substantial completion of the project. — Photo courtesy RDEK

The Tie Lake Dam project is substantially complete and the new dam structure is in place.

Construction started earlier this fall and included raising the height of the dam to allow for more freeboard; installation of seepage control and a new spillway. “The larger size of the dam has reduced the risk of the dam being overtopped by high water as has nearly happened a couple of times in the past few years,” explains Engineering Technician Brian De Paoli.

As part of the project, the weir, known as a Cippoletti weir due to the v-shaped notch in its design, has been fenced. Although the dam height has been increased, the average lake level is not expected to change. “The dam height will help prevent issues during high water and flooding; however, at this time the structure is not intended to raise the level of the lake beyond the previous seasonal norms,” adds De Paoli.

RDEK Engineering Technician shows Electoral Area B Director Stan Doehle the new weir that has been installed as part of the Tie Lake Dam project.

RDEK Engineering Technician shows Electoral Area B Director Stan Doehle the new weir that has been installed as part of the Tie Lake Dam project. — Photo courtesy RDEK

“It is great to see this project completed. We now have a dam structure that meets the safety objectives of the Dam Safety Officer, and that will meet the needs of the community for years to come,” says Electoral Area B Director Stan Doehle. “We are also very grateful to the Community Works Fund for funding 86% of the project.”

Although the disturbed areas around the project site have been re-seeded, the RDEK will be back on site in the spring to undertake further vegetation measures and monitor the progress of the seeding.

“We would like to thank the residents and property owners of Tie Lake for their patience as we worked through the process of rebuilding the dam. We also would like to thank our consulting engineer Associated Engineering and our contractor Ironclad Construction for their efforts throughout the project,” adds De Paoli.

The total cost for the project was $450,000.

Related articles

Kootenay BizBlog, East Kootenay, West Kootenay Publisher Keith Powell steps into retirement

After 42 years of involvement in the local publishing scene, Kootenay Business publisher Keith Powell is retiring

Kootenay BizBlog, East Kootenay, West Kootenay, Developments, Financial Outdoor gathering spaces enhanced

Trust provides over $1.9 million for 12 community projects

Kootenay BizBlog, East Kootenay, Technology Online Portal Seeks to Test Internet Connectivity Performance Across the Basin and Boundary

The online testing portal is designed to measure internet connections speeds and get a better understanding of current broadband services

View all articles

Comments